Projects: SR 0080, Section 10S: Design-Build
| |
|
|
| Client: |
James D. Morrissey, Inc. |
| Location: |
Monroe County, Pennsylvania |
| Owner: |
PennDOT, Engineering District 5-0 |
| Type/Size: |
1.8 Mile Full-Depth concrete Pavement Replacement, Design-Build |
| Services: |
Design-Build Partnerships
|
|
This second stage of the I-80/I-380 interchange project includes the reconstruction of the full-depth concrete pavement along 1.1 miles of SR 0080 WB and 0.7 miles of SR 0380 NB in Monroe County. This stage of the interchange project includes two important changes: a NPDES Permit is required and lane closures are restricted on a number of holidays and regional events. All construction requiring long-term lane closures must be completed no later than October 6, 2006, which provides a 7-month construction schedule. Construction will be interrupted for four (4) holidays and two (2) Pocono Raceway events.
« Back
| |
|
|
|
|
|