Projects: SR 0080, Section 10S: Design-Build

Client:    James D. Morrissey, Inc.
Location:    Monroe County, Pennsylvania
Owner:    PennDOT, Engineering District 5-0
Type/Size:    1.8 Mile Full-Depth concrete Pavement Replacement, Design-Build
Services:    Design-Build Partnerships


This second stage of the I-80/I-380 interchange project includes the reconstruction of the full-depth concrete pavement along 1.1 miles of SR 0080 WB and 0.7 miles of SR 0380 NB in Monroe County. This stage of the interchange project includes two important changes: a NPDES Permit is required and lane closures are restricted on a number of holidays and regional events. All construction requiring long-term lane closures must be completed no later than October 6, 2006, which provides a 7-month construction schedule. Construction will be interrupted for four (4) holidays and two (2) Pocono Raceway events.